PACKAGE 7 - Sub Work: 5 - Reconstruction of 3nos. of culverts across the Olandai surplus course drainage Canal in MGR Nagar Street, Siva Vishnu Nagar street and Jayam Nagar Culvert in Puducherry.

Name of Work
PACKAGE 7 - Sub Work: 5 - Reconstruction of 3nos. of culverts across the Olandai surplus course drainage Canal in MGR Nagar Street, Siva Vishnu Nagar street and Jayam Nagar Culvert in Puducherry.
Sector
Storm Water Drain
Scope of the Work
Project Cost
0.30 Cr.
Work Order Issued Date
30-03-2022
Project Implementation Agency
PWD
Period for completion of work
Project Contractor
Work Progress
30
Financial Progress
.05

Project Location

(Click this icon in map to get more details)

Project Highlight