PACKAGE 12 – Sub Work: 1 – Construction of RCC “U” drain along Olandai surplus course and North of Olandai tank, strengthening bunds of Olandai tank including construction of box culvert at common bund and surplus course from byepass pipe culvert upto Murungapakkam surplus, Puducherry.

Name of Work
PACKAGE 12 – Sub Work: 1 – Construction of RCC “U” drain along Olandai surplus course and North of Olandai tank, strengthening bunds of Olandai tank including construction of box culvert at common bund and surplus course from byepass pipe culvert upto Murungapakkam surplus, Puducherry.
Sector
7.07
Scope of the Work
Project Cost
7.07 Cr.
Work Order Issued Date
21-09-2021
Project Implementation Agency
PWD
Period for completion of work
Project Contractor
Work Progress
28
Financial Progress
.1

Project Location

(Click this icon in map to get more details)