Improvement to Primary Storm Water drain - PACKAGE 3

Name of Work
Improvement to Primary Storm Water drain - PACKAGE 3
Sector
Storm Water
Scope of the Work
Construction of RCC precast Box culvert for Mettuvoikkal at Anna Nagar (opposite Housing Board) in Ellapillaichavady Road junction, Puducherry.
Project Cost
2.31 Cr.
Work Order Issued Date
09-07-2021
Project Implementation Agency
PWD
Period for completion of work
6 Months
Project Contractor
SR. Neelamegham
Work Progress
30
Financial Progress
.08

Project Location

(Click this icon in map to get more details)

Project Highlight

Improvement to Primary Storm Water drain  - PACKAGE 3