Conversion of 2 pole transformer Phase- I

Name of Work
Conversion of 2 pole transformer Phase- I
Sector
Energy
Scope of the Work
Provision of 26 nos of compact sub station along the Gran canal. This results in complete avoidance of Power outage caused by overhead cables/oil transformers, improved safety, reliable power supply
Project Cost
10.22 Cr.
Work Order Issued Date
26-05-2021
Project Implementation Agency
PED
Period for completion of work
11 Months
Project Contractor
Raja Electricals, Karnataka
Work Progress
50
Financial Progress
4.06

Project Location

(Click this icon in map to get more details)

Project Highlight

Conversion of 2 pole transformer  Phase- I 