Improvements to Primary Storm Water drain - PACKAGE 8

Name of Work
Improvements to Primary Storm Water drain - PACKAGE 8
Sector
Storm Water
Scope of the Work
Improvement and linking the Krishna Nagar Phase-III drain to the Krishna Nagar Phase-II drain running through Danakantharaj School, Puducherry
Project Cost
0.97 Cr.
Work Order Issued Date
25-09-2020
Project Implementation Agency
PWD
Period for completion of work
6 Months
Project Contractor
K. Muthukumaran
Work Progress
70%
Financial Progress
0.26

Project Location

(Click this icon in map to get more details)

Project Highlight

Improvements to Primary Storm Water drain - PACKAGE 8 